February 2024 : site supervision mission in Senegal
3rd intervention by Eric, AVe "project management" expert at Djilas Sénégal
For the 3rd time, Eric, an AVe expert specializing in building management, visited Djilas to check on the progress of the dispensary and maternity hospital construction site. The company is doing a good job, with work scheduled to take 10 months, but progressing more slowly than expected.
the entrance to the current Djilas health center | Progress of work on the new center |
Completion is scheduled for the end of April 2024, with inauguration scheduled for the end of 2024.